Timeline for Center
- Fundraising campaign to raise an initial 3 to 5 million
- Register project with US Green Builders Council for LEED certification November, 06
- Begin Schematic Design – January 07
- Begin Construction Documents – February 07
- Project Bidding – April 07
Projected groundbreaking date, July, 2007. Anticipated construction 18 Months
Currently, a conceptual design by Cubellis Ecoplan for the proposed Center has been completed and has won an award from the NJ chapter of the American Institute of Architects.
|